Joint Road Rehabilitation Program

Since 2019 the Village has partnered with Mundelein and Vernon Hills for a joint bid road rehabilitation program in order to receive advantageous competitive unit price bids based upon an “economies of scale” from larger contract quantities.  Peter Baker & Son, Co. was awarded the contract on March 23, 2021.  Work began in mid-July 2021 and will be complete by Fall 2021.  The Pavement Assessment Report completed in 2019 was utilized to select the following streets that will be rehabilitated.  Click Here to view the Pavement Assessment Report.  

Street  From  To Approx. Length
Victory Drive  Butterfield Road  Dead End 0.27 miles
Crane Blvd. Butterfield Road  Dead End 0.18 miles 
Stevenson Drive  Lothair Drive Dead End  0.15 miles 
Pine Tree Lane  Butterfield Road  Dead End  0.28 miles 
Nordic Court  Crane Blvd. Crane Blvd.  0.36 miles 
Carter Street  W. Austin Avenue  Dead End  0.16 miles 
N. Stewart Avenue  W. Maple Street  Park Avenue (Rte. 176)  0.12 miles 
Wedgemere Place  E. Rockland Road  E. Lincoln Avenue  0.09 miles 
    Total  1.63 miles 
CONSTRUCTION ADVISORIES

August 3, 2021

2021 Street Improvements Project - Crestfield Avenue, Fairlawn Avenue, Carter Street, N. Stewart Avenue, Wedgemere Place and Victory Drive

Earlier this week the concrete contractor completed all pavement patching, and the final preparatory work for the paving operation is scheduled to be started on Tuesday, 8/3/2021. After all preparatory works are done, the street will be cleaned, and prior to applying a prime coat (tar -like material).  The prime coat allows the surfacing to bond completely with the first layer of pavement.  

 Weather permitting, the first layer of asphalt is scheduled to be placed on Monday, August 9, 2021.  Please drive slowly on the fresh oil and avoid pulling into concrete aprons until the oil has curedBoth placement of oil and asphalt are very sensitive to moisture, and wet conditions may delay one or both of the operations. The Village of Libertyville requests that all vehicles are off the streets listed above from 7am to 5pm on days when priming or paving work is in progress. Driveways adjacent to the operations may be temporarily inaccessible while the operations move past.  

 We appreciated your continue cooperation.  Should you have any questions regarding the construction, please call the Engineering Division Office at (847) 247-5435, between 8:00 a.m. and 5:00 p.m. For any problems which may develop after hours, please call the Police non-emergency number (847) 362-8310, and they will contact the proper personnel for follow-up.

August 3, 2021

2021 Street Improvements Project - Pine Tree Lane and  Nordic Court

Earlier this week the concrete contractor completed all pavement patching, and the final preparatory work for the paving operation is scheduled to be started on Tuesday, 8/3/2021.  After all preparatory works are done, the street will be cleaned, and prior to applying a prime coat (tar -like material).  The prime coat allows the surfacing to bond completely with the first layer of pavement.  

Weather permitting, the first layer of asphalt is scheduled to be placed on Saturday, August 7, 2021.  Please drive slowly on the fresh oil and avoid pulling into concrete aprons until the oil has curedBoth placement of oil and asphalt are very sensitive to moisture, and wet conditions may delay one or both of the operations. The Village of Libertyville requests that all vehicles are off the streets listed above from 7am to 5pm on days when priming or paving work is in progress. Driveways adjacent to the operations may be temporarily inaccessible while the operations move past.  

We appreciated your continue cooperation.  Should you have any questions regarding the construction, please call the Engineering Division Office at (847) 247-5435, between 8:00 a.m. and 5:00 p.m.  For any problems which may develop after hours, please call the Police non-emergency number (847) 362-8310, and they will contact the proper personnel for follow-up.